Bid Centre
The Bid Centre is where a quote can be produced to give a value to the Job being created
a) Options > Set Bid Options
b) Bid Setup > Item Totals
- Select the Materials to be included in the quote
- Add a Value to the Drawers and Roll Outs
c) Set a Price for the Doors and Drawer Fronts
- Close Out of the Job and return to the Splash Screen > Door Catalog
- Select the Door Style
c) Door Catalog Editor - Edged Slab
- General Info - Cost
c) Door Catalog Editor - Edged Slab
- Material tab - Add Per Door / Add Per SqM / Minimum Cost
d) Bid Set Up > Length Totals
- Show the Total for your Cabinets > Base, Upper and Tall - We have used this rate as a value per lineal metre and it equates to minutes at $60.00 per hour in order to give us the hours for the job
- Show These Molding Totals > Values per Meter to reflect the minutes required to run the material
e) Bid Setup > Header
- Tick the boxes applicable
- Add Your Company Detail in the text box
f) Bid Setup > Tax Rate - select a percentage markup which you wish to apply to the job
- Add Text for your footer in the text box
g) Bid Setup > Extra Line Items
- Add other items not already included in your quote as shown below
- There are only 3 Line Items which capture the 'markup value'
- Items listed in the Non-Taxable Line Items area will require the 'markup' value added to it at this level
h) Basic Report has been produced
- To calculate the labour > add the minutes in the Cabinets, Doors & Drawers and Molding Sections - total then divide the total by 60 = total hours
- i.e. Total of 1896 mins divided by 60 = 31.6 hours = 31hours 36mins
- Your Bid for this Job under Materials and Labour equation = $6692.00 + 33%(tax) Markup = an overall total of $9150.00 + GST
- This report can be either printed from the print icon on the top shortcut bar or Export to RTF to be amended in Word